Hani Solon

Dispute Resolution, Litigation & Construction Law in Queensland

Construction disputes in Queensland

Construction disputes in Queensland are shaped by two sets of rules. The Building Industry Fairness (Security of Payment) Act 2017 (the BIF Act) keeps progress payments moving on strict business-day deadlines, and the Queensland Building and Construction Commission (QBCC) regulates licensing, defective work and home warranty insurance. This page explains both in plain English.

Much construction dispute resolution happens outside the courts. Commercial payment disputes usually turn on BIF Act adjudication, while disputes between home owners and builders start with the QBCC and, if they don’t resolve, go to QCAT. For court processes, time limits and enforcing a judgment, see litigation in Queensland.

Payment claims and payment schedules under the BIF Act

The BIF Act is a ‘pay now, argue later’ system. A payment claim must identify the construction work and state the amount claimed. It doesn’t have to mention the Act, so an ordinary invoice can be a payment claim. If the contract doesn’t set a valid due date, payment is due 10 business days after the claim is made.

A respondent that won’t pay in full must give a payment schedule within 15 business days, or any shorter time in the contract, stating the amount it will pay and all its reasons for paying less. Miss that deadline and it becomes liable for the full amount, with no right to respond in adjudication. The days from 22 December to 10 January aren’t business days.

Adjudication

Adjudication is a decision on the papers by a registered adjudicator, made through the QBCC’s adjudication registry. The claimant’s deadline to apply depends on what happened:

  • payment schedule for less than the claim: 30 business days after receiving the schedule
  • scheduled amount not paid: 20 business days after the due date
  • no schedule and no payment: 30 business days after the later of the due date and the last day for a schedule

A respondent to a standard claim must respond by the later of 10 business days after receiving the application and 7 business days after notice that the adjudicator accepted it. The decision follows within 10 business days (15 for complex claims over $750,000) and is interim: the final position can be argued later.

Subcontractors’ charges

A subcontractor’s charge lets an unpaid subcontractor secure the money it is owed against money payable further up the contracting chain, usually by the principal to the head contractor. The subcontractor gives a notice of claim of charge, with the work and the amount certified by a qualified person, such as a registered architect or professional engineer.

The notice must be given within 3 months after practical completion of the work (or, for a claim only for retention money, within 3 months after the defects liability period ends). If the claim is disputed, proceedings must generally start within 1 month of the notice, or the charge is lost. Charges don’t apply to domestic building work on a detached house for an individual.

The QBCC: licensing, directions to rectify and home warranty

The QBCC licenses contractors, deals with defective work complaints and runs the Queensland Home Warranty Scheme.

QBCC licensing

Building work valued over $3,300 needs a QBCC licence, and some work, such as plumbing, drainage, gas fitting and fire protection, needs one at any value. An unlicensed contractor generally can’t use the BIF Act to get paid for licensed work. A person who becomes bankrupt, or who was a director, secretary or influential person of a construction company in the 2 years before it went into liquidation or administration, is excluded from holding a licence for 3 years.

Directions to rectify

Before lodging a defective work complaint, give the contractor written notice of each defective or unfinished item and a timeframe to fix it. If the QBCC finds defective work, it can direct the contractor to rectify it, usually within 35 days, and failing to comply can lead to fines and disciplinary action. You have 28 calendar days to seek an internal review of a reviewable QBCC decision, and an application for QCAT review must be made within 28 calendar days of the original or internal review decision.

Home warranty insurance

Residential construction work valued at more than $3,300 must be covered by the Queensland Home Warranty Scheme, and the contractor pays the premium. Cover lasts 6 years and 6 months and can respond to non-completion, defects and subsidence, but each type of claim has its own time limits. See what home warranty insurance covers.

Domestic building disputes: the QBCC first, then QCAT

Disputes between home owners and builders don’t start in court. QCAT decides domestic building disputes, with no monetary limit, but the parties must first take part in the QBCC’s dispute resolution process. The QCAT application must include a letter from the QBCC about the outcome, and without it QCAT can refuse or dismiss the application.

The QBCC’s early dispute resolution aims to settle the disagreement through facilitation. QCAT also hears commercial building disputes of up to $50,000, or more if both parties consent in writing. The BIF Act generally doesn’t apply to a home owner’s contract for work on the home they live in or plan to live in.

Defects

How defective work is pursued depends on the contract and who you are. Home owners usually start with written notice to the builder, then a QBCC complaint and, if needed, a home warranty claim or a QCAT application. On commercial projects, defects are usually dealt with under the contract’s defects liability clauses, and a respondent that withholds a progress payment because of defects must give its reasons in the payment schedule.

Ordinary time limits still apply. A claim for breach of contract generally must start within 6 years of the breach, and for negligence time runs from when the loss is first suffered, which can be years after the work. Dated photos, expert reports and correspondence are the core evidence.

Variations

Variations are one of the most common causes of serious building disputes. In a domestic building contract, the contractor must give the owner the variation in writing, stating any change to the contract price and a reasonable estimate of any delay. It must be given before the variation work starts, or within 5 business days after both parties agree to it, whichever comes first, and the owner must respond in writing.

In commercial work the contract sets the process, often with strict time limits for notices that also apply to extension of time claims. A disputed variation in a payment claim must be answered, with reasons, in the payment schedule. See the QBCC on contract variations.

Termination

Ending a building contract carries real risk. A party that terminates without a proper basis, or without following the contract’s process, may itself be treated as repudiating the contract and end up liable for damages. Most contracts set out a process, often a show-cause notice and a period to respond, and it should be followed exactly. Get advice before sending or answering any termination notice.

For domestic building contracts, owners generally have a cooling-off period of 5 business days, starting the day after they receive a signed copy of the contract (and, for contracts of $20,000 or more, the QBCC’s guide). Withdrawing usually costs $100 plus the contractor’s reasonable out-of-pocket expenses.

Retention and deposits

Deposits on domestic building contracts are capped at 10 per cent for contracts from $3,301 to $19,999 and 5 per cent for contracts of $20,000 or more. Up to 20 per cent is allowed where more than half the work, by value, is made off-site. Paying more, or earlier, than the contract allows can affect home warranty cover.

Retention money, held back as security for defects, is released as the contract provides. A subcontractor claiming a charge over retention money must start any proceedings within 4 months after it becomes payable. The wider rollout of Queensland’s trust account rules was paused in 2025, so they apply only to eligible Queensland Government contracts of $1 million or more and other contracts of $10 million or more.

Guides on this topic

In-depth guides to Queensland building and construction disputes, newest first.

General information only, not legal advice. Current as at 27 November 2026.