Payment claim without a signed contract: Supreme Court upholds a blocklayer’s $79,531.87 adjudication

Case: CGC Qld Pty Ltd v Ziegel Co Pty Ltd [2026] QSC 224 · Supreme Court of Queensland · Hindman J · decided 22 September 2026

On Queensland sites the paperwork often trails the work, and a replacement subcontractor can be paid for months with nothing signed. This decision deals with whether, once that relationship sours, a payment claim without a signed contract can support a security of payment adjudication. Here a head contractor paid four claims, left the fifth unpaid, and lost $79,531.87 at adjudication.

The Supreme Court upheld the award. The parties had drifted into a construction contract under the Building Industry Fairness (Security of Payment) Act 2017 (BIF Act), their claiming pattern had fixed the reference date, and submissions lodged 24 minutes after the adjudicator’s deadline did not void the decision. The judgment has been selected for reporting.

It matters to head contractors who let work run ahead of the paperwork, and to subcontractors who step in for a related company in trouble.

A restructure, an unsigned novation and five payment claims

CGC Qld Pty Ltd subcontracted the blockwork to Brizmasonry Pty Ltd on 24 July 2024 [10]. In November 2024 Brizmasonry said it was restructuring, that a related company, Ziegel Co Pty Ltd, would do the work, and asked CGC to consent to a novation [12]. CGC never signed. Brizmasonry went into external administration and lost its licence, and Ziegel obtained its own [13].

Ziegel started work in late January 2025 and on 7 February sent a schedule of rates ($9 a block, $125 an hour for labour). CGC never replied [14] to [16]. Ziegel then claimed monthly from February to May 2025, mostly at the scheduled rates, and CGC paid each claim in full or in part [17] to [26]. CGC’s own certificates of 1 May and 1 July 2025 recorded that no subcontract had been signed [24], [27].

On 29 August 2025 Ziegel issued PC05 for $81,666.97 excluding GST [28]. CGC did not pay. On 25 November 2025 the adjudicator decided $79,531.87 was payable, and CGC paid that sum into court and sought to have the decision declared void [1], [43].

Three challenges to the adjudicator’s jurisdiction

An adjudication decision cannot be set aside for an ordinary error of fact or law. CGC had to show jurisdictional error: that something the BIF Act makes essential to the adjudicator’s power was missing [6], [8]. It argued that there was no construction contract; that PC05 was given before a reference date had arisen; and that the adjudicator relied on late submissions that were not properly made [2].

How a payment claim without a signed contract survived all three

Under s 64 of the BIF Act, a construction contract includes any contract, agreement or other arrangement to carry out construction work for another party [46]. Wide as that is, it still requires “a sufficiently concluded state of affairs which is bilateral” [49]. In GCB Constructions Pty Ltd v SEQ Formwork Pty Ltd [2023] QSC 71 there was only a request for labour, with no agreed rates, and the test was not met [52] to [54].

Here the price made the difference. Ziegel worked at CGC’s request, CGC had paid four claims on the schedule of rates, and the same work at the same rates made up most of PC05 [58]. By the time of PC05 there was a construction contract, or at least an other arrangement with the necessary qualities [57]. Parties can drift into that relationship by the time the claim is served [55], [56].

An agreed method of valuing the work may be enough. But “if the right to payment rests only on a restitutionary basis, I cannot see how there could exist a construction contract as defined in the BIF Act” [63]. A subcontractor in that position may have other ways to recover money for work done, but not adjudication.

On reference dates, s 67(1) applies the date stated in or worked out under the contract, and falls back to the last day of each month only if the contract is silent [66]. Ziegel’s claims clustered around the 25th, and CGC itself wrote in April and August 2025 asking for claims before the 25th [68] to [70]. The parties had agreed, partly expressly and partly by conduct, on the 25th of each month, and PC05 was validly made [67], [71] to [73].

Ziegel’s further submissions, requested by the adjudicator, arrived 24 minutes after his deadline [41], [42]. An adjudicator may consider only submissions properly made under s 88(2), and relying on others can be jurisdictional error [75], [76]. But this deadline was the adjudicator’s own, set under s 84, and s 84(4) provides that a party’s failure to make a submission in time does not affect the power to decide [74], [78]. Meeting such a deadline “is not a basic and essential requirement of the BIF Act” [80]. Whether late material is properly made is for the adjudicator, and by considering it he implicitly decided that it was [78], [81].

The application was dismissed [86], with proposed orders releasing the money in court to Ziegel and for CGC to pay Ziegel’s standard costs.

What head contractors and subcontractors should do differently

For head contractors and principals:

  • An unsigned subcontract will not keep you outside the BIF Act if you direct work, receive a schedule of rates and pay claims priced on it. If you reject a replacement entity, say so in writing at the start.
  • Check what your own systems tell subcontractors. Routine reminders to claim before the 25th helped fix the reference date here.
  • Answer each payment claim with a payment schedule on time, stating what you will pay and why. That beats arguing months later that there was never a contract. Our guide to how payment claims work under the BIF Act sets out the steps.

For subcontractors:

  • Get the price agreed in writing even if the contract is not signed. A schedule of rates the other side acted on was decisive for Ziegel.
  • If you take over work from a related company, press for a signed novation or new subcontract, and make sure the company doing the work holds the right licence first.
  • Your regular claiming day may become your reference date.
  • Meet adjudicators’ deadlines. Ziegel’s lateness was forgiven only because the adjudicator chose to accept the material.

General information only, not legal advice. Current as at 13 October 2026.